2015

2015: Passavant Energy & Environment - Nablus West WWTP

Due to unexpected failure of the SCADA system, PCS intervened to redeploy the SCADA system in the Nablus West WWTP. All software including but not limited to SIMATIC TIA PORTAL Step7 and WinCC have been installed. Data logging, trending and reporting was carried out via Acron Software. Morever, because Waste Water Treatment Plant SCADA system availability is crucial for every plant; PCS have deployed redundant solution on the server via RAID 1 configuration and scheduled automatic backup of plant data.

2015: Water Supply and Sewage Facilities Improvement for Bethlehem - Beit Jala & Beit Sahour Area

PCS was awarded "Water Supply and Sewage Facilities Improvement for Bethlehem - Beit Jala & Beit Sahour Area" area; the project is financed by AFD (Agence Française de Développement) and NRO (Netherlands Representative Office). The main contractor is Madanat Contracting Co. 

The project consists construction of new reservoirs and network lines, and also rehabilitation of old reservoir and pump stations. PCS will be in charge of the whole Automation and SCADA connectivity system.


2015: Jericho Municipality (Water Flow Monitoring)

Jericho municipality had several issues with their old ultrasonic clamp-on flowmeter measuring system, as a result, they couldn’t control their water resources. To solve this problem, PCS have installed SIEMENS Electro-magnetic flowmeter with an accuracy of 0.2% to meet the application requirement.

 

 Furthermore, our team have connected the flowmeter via the GSM/GPRS network to make the data available not only in Center Control Room, but also via mobile phone for site operators.


2015: Al Reehan Waste-Water Treatment Plant 

MBR wastewater treatment plant at Reehan uses the membrane technology for treatment, we were in charge of replacing the HMI for the Decanter Device.


2015: Ras Tawil & Uddeisa Water Infrastructure and Safi Booster Station 

PCS was awarded the project in the Hebron area; the project is financed by USAID and the main contractor SAQQA & KHOUDARY Co. Ltd. awarded the automation and SCADA part to PCS.

 

Works are to be executed in Al-Safi reservoir, Ras Al Tawil and Al Uddeisa pipeline, it consists of installing flowmeters, pressure transmitters and differential pressure switches to be able to monitor reservoirs water flow and status.

 

PCS was able to answer to all project requirements with ease due to our strong partnership with SIEMENS and we offered MAG8000 battery powered flowmeters with GSM/GPRS connectivity to be able to transmit vital data to the SCADA Main Control Room located in Ramallah Water Department of West Bank.

 

The added is integrated in the Main SCADA Control in order to be able to get valuable data from the installed field instrumentation. Next stages of this project is to be able to achieve not only monitoring but also control of pumping stations and reservoirs.

 


2015: Hebron WWTP Access Road 

This is another project which is similar to Ras Tawil & Uddeisa water infrastructure it consists of installing flowmeters, pressure transmitters and differential pressure switches to be able to monitor reservoirs water flow and status.

 

PCS was able to answer to all project requirements with ease due to our strong partnership with SIEMENS and we offered MAG8000 battery powered flowmeters with GSM/GPRS connectivity to be able to transmit vital data to the SCADA Main Control Room located in Ramallah Water Department of West Bank.

 

The added is integrated in the Main SCADA Control in order to be able to get valuable data from the installed field instrumentation. Next stages of this project is to be able to achieve not only monitoring but also control of pumping stations and reservoirs.